London, United Kingdom · Facade and material reuse

1 Triton Square

A wider retrofit case study shows how facade refurbishment and structural retention can support a larger building.

Published and source reviewed . Reported by Arup: 1 Triton Square ↗. Source date: Undated engineer page; checked 2026-10-03.

Reported results and their boundaries

Source-reported metrics, not independently audited
ValueMeasureScope and limits
40,000 tonnesReported carbon savingArup comparison with a typical new build. The public page uses ‘carbon’ without a complete lifecycle-module breakdown.
3,500 m²Facade panels refurbishedPanel refurbishment at a nearby temporary factory; not the total building floor area.
>2,400 tonnesReported facade carbon savingFacade reuse comparison with a new facade. A component of the project account, not a quantity to add to the whole-project saving.

Inspect, refurbish, reinstall

Arup describes removing facade components, inspecting and cleaning them, then reinstalling them. The retained superstructure was strengthened to accommodate three additional floors. This is a useful retrofit precedent outside the top-100 skyscraper ranking.

A boundary before a leaderboard

A whole-project estimate and a facade-only estimate answer different questions. Comparing either number with a new tower requires matching floor area, service life, lifecycle stages and the assumed replacement scheme. Retention also requires condition surveys and verification of existing connections; a reuse percentage alone cannot show whether a component is suitable for its new loads.

The interpretation above identifies questions for engineering review. It does not fill gaps in the source with assumed performance data. Read the primary account ↗